Heritage Kalka-Shimla toy train services to restore after 82 days from Oct 3

Heritage Kalka-Shimla toy train services to restore

Heritage Kalka-Shimla toy train services to restore

Share This News

Shimla, Oct 3 : UNESCO Heritage Kalka Shimla Railway line commissioned by the Britishers in 1908, will be restored for the people again after remaining closed for 82 days due to washing away of track in the monsoon season.

Additional SP Northern Railway Tourists Traffic Narvir Rathore told UNI that the track inspection was done today around 1200 hours and decided to restore the train services.


He said that the fleet of two trains which were plying between Kalka and Taradevi earlier would now be extended to Shimla Railway station. He said that the railway would ply two services between Kalka and Shimla and vice versa from Tuesday.

The track was put to test on Monday which declared fit for plying of heritage toy trains successfully. Railway officials completed a trial run from Kalka to Shimla Railway Station on Monday.

The toy train is now set to resume its regular schedule on the 96 km long Kalka-Shimla heritage rail track after being halted for about 82 days.

Reportedly, a 7.39 meter long bridge has been erected on the affected portion above Shiv baudi of summer hill in Shimla. The bridge was installed in only 16 days by around 200 workers and engineers from Delhi, Ambala and Jalandhar.
The train services had resumed up to Taradevi Railway Station from Kalka last week. Furthermore, a bridge near the rain-affected Shiv Bowri site is now ready to be commissioned, signaling the restoration of full service.

The Northern Railway service primarily caters to tourists, providing daily transportation from Kalka to Shimla and vice versa. The recent monsoon rainy season took a toll on this world heritage track, causing damage with uprooted trees, landslides, and flash floods affecting railway property.
Given the significance of this train service for luxury tourists and the hospitality industry, both the local administration and the Northern Railway have been under pressure to ensure prompt restoration of service on the track.

Additionally, the recent construction of the Kalka-Shimla Four Lane project and the widening of other link roads have posed threats to the track’s stability, making it susceptible to debris and flash floods.